titleCalculation notes

1 Work stoppage is an issue satisfying a blocked status defined in Project Settings>Data Sources>Task Tracking System>Scope Management criteria 'Work stoppages tracking'.

2 If an issue lives all month long, the average amount of hours will be the same for a particular month for different projects if a number of work stoppages doesn't change during a month.

3 Chart shows Work Stoppage for each period, but a drill down shows total time which a work item has spent in Work stoppage state (no matter which period was selected the result will be same).


Info
titleExample

Case 1: number of issues remains unchanged during the month:

  • Calculation for 612 work stoppages existing the whole month:  31 days*24 hours*612 issues/612 issues= 744 hours.

Case 2: number of issues changes during the month:

  • Total lifetime: 3 days*24 hours*1 issue + 2 days* 24 hours*1 issue + 31 days * 24 hours * 5 issues = 3840 hours.
  • Average lifetime: 3840 hours/7 issues= 549 hours.

...