Units of Measure for metrics

All of the aggregated metrics are calculated based on the set units of measure per project. For example, if you set it to "Story Points", them Backlog Health will be counted based on story points estimation.

You can change the setting in Project Configuration → Project Settings

Backlog Health

This aggregates the values of the metric Backlog Health.

Sprint Scope Change

This aggregates the values of the metric Sprint Plan Change.

...

Aggregation goes by the value of the last sprint for the project 

Commitment Rate

This aggregates the values of the metric Commitment Rate.

Forecast

This aggregates the values of the metric Delivery Forecast via Burn-up.

Info
titleCalculation notes
  1. Metric displays Forecast with Scope Creep value.
  2. Forecast is calculated for whole project.
  3. Units of Measure is based on setting in "Project Configuration → Project Settings → What is the primary units of measure on this project?"
  4. If Units of Measure is Story Points, then metric is calculated based on issues types according to Data Source Configuration → Task Tracking System → Scope Management →  "ISSUE TYPES EXPECTED TO BE ESTIMATED IN STORY POINTS". If it is not empty, then calculation is performed for this issues. If it is empty, then all issue types available for the project are calculated.
  5. If Units of Measure is Hours or Items, then metric is calculated based Burn-up chart setting → View in

Velocity trend

Velocity trend shows a percentage of changing average velocity within last 4 weeks in comparing to the average velocity in the last 13 weeks (rolling average).

...

Info
titleCalculation notes
  1. Only completed weeks are calculated, no future ones;
  2. End of a week is a UTC midnight between Saturday and Sunday (i.e. as per US notation);
  3. Metric value could be different from values on Average Velocity due to Average Velocity is displays rounded values.
  4. Metric is calculated if unit start date more than 4 weeks ago. If less then "No Data" is displayed on a micro-metric.

Closed vs Open Defects

Closed vs Open defects shows a difference of Fixed and Opened defects (over last 4 calendar weeks) as a percentage to a number of all open defects in the backlog as of 4 calendar weeks back.

...