This section describes how to update a target progress through check-in. You can check in a target from the following Planner entities: 

  • Planner List view

  • Target information dialog boxsidebar

  • Planner Timeline view

1. List View Check In

...

  1. In the right or the required target row, click (ellipsis), and then click Check in. The Check-In dialog sidebar opens.

  2. In the Current Progress specify the target progress in %.

  3. Click Check-In.

Info

You cannot directly update the progress of a parent target having child targets. To do that you need to update the progress of the child targets.

...

2. Target

...

sidebar Check In

To check in a target in the List view:

  1. Open dialog box the sidebar of the required target.

  2. In the upper left, click Check in. The Check-In dialog opens.

  3. In the Current Progress specify the target progress in %. See Fig. 2.

  4. Click Check-In.

Info

You cannot directly update the progress of a parent target having child targets. To do that you need to update the progress of the child targets.

...

3. Planner Timeline view

To change the progress of a target:

  1. Pause on a target. The system displays the progress grip (triangle) on the target line.

  2. Drag the progress grip.

...