This section describes how to link a target with other targets to see the entire process of achieving the planned goals.
You can link targets in two Planner entities:
Target's dialog boxsidebar
Gantt chart
1. Link in the
...
sidebar
The information dialog box sidebar of any target contains three tables intended for linking the target with other targets.
Type of link | How to |
---|---|
Includes |
|
Contributes To |
|
Dependencies |
|
...
Pause on a target. The system displays points on both ends of the target.
Click the point and drag the connector to a required target to link.
Drop the connector on the required target. The Add Connection dialog box sidebar opens.
Specify the type of link: Hard link or Soft link.
If you selected Hard link, specify the type of dependency, as one of the following:
Finish to start
Start to finish
Finish to finish
Start to start
Click Save.
...