This section describes how to link a target with other targets to see the entire process of achieving the planned goals.
You can link targets in two Planner entities:

  • Target's sidebarCreate View

  • Full View (Target’s sidebar)

  • Gantt chart

1. Link

...

via Create or Full View 

The information sidebar of any target contains three two tables intended for linking the target with other targets.  

Type of link

How to

Includes 

  1. Create a new target

Contributes To 

  1. Open the sidebar of a new or existing target.

  2. In the Contributes To “Includes” table , click Add Item, or Add Objective.

  3. Choose a target type.

  4. In the Title field, start typing the name of a required target, and then select the name from the system prompt.an existing target or enter a new target’s name

  5. Select a target (an existing one) or click “Create New” to create a new child target

Dependencies

  1. Open the sidebar of a new or existing target.

  2. In the Contributes To “Time Dependencies” table , click Add Item, or Add Dependency.

  3. In the Title field, start typing the name of a required target, and then select the name from the system prompt.

...

2. Link

...

via Gantt Chart

This section describes how to link targets in the Gantt chart by means of dragging a connector between targets.

...