The information sidebar of any target contains two tables intended for linking the target with other targets.  

Link Type of link

How to link a target

Includes 

  1. Open the sidebar of a new or existing target.

  2. In the “Includes” table click Add.

  3. Choose a target type.

  4. In the Title field, start typing the name of an existing target or enter a new target’s name

  5. Select a target (an existing one) or click “Create New” to create a new child target

Dependencies

  1. Open the sidebar of a new or existing target.

  2. In the “Time Dependencies” table click Add.

  3. In the Title field, start typing the name of a required target, and then select the name from the system prompt

...

This section describes how to link targets in the via Gantt chart by means of dragging a connector between targets.

To link a target:

...

Hover a target. The system displays points on both ends of the target.

  1. Click the point and drag the connector to a required target to link.

  2. Drop the connector on the required target. The Add Connection sidebar opens.

  3. Specify the type of link: Hard link or Soft link.

  4. If you selected Hard link, specify the type of dependency, as one of the following:

    • Finish to start

    • Start to finish

    • Finish to finish

    • Start to start

  5. Click Save.

...