Units of Measure for metrics
All of the aggregated metrics are calculated based on the set units of measure per project. For example, if you set it to "Story Points", them Backlog Health will be counted based on story points estimation.
You can change the setting in Project Configuration → Project Settings
...
Backlog Health
This aggregates the values of the metric Backlog Health.
Sprint Scope Change
This aggregates the values of the metric Sprint Plan Change.
Counting method:
Code Block | ||
---|---|---|
| ||
Sprint Scope Change = (abs(added_items) + abs(removed_items))/items_in_sprint_on_sprint_start |
Where
added_items - number of tickets added to sprint since sprint start
removed_items - number of tickets removed from sprint since sprint start
items_in_sprint_on_sprint_start - number of tickets in sprint at the moment of sprint start
Aggregation goes by the value of the last sprint for the project
Commitment Rate
This aggregates the values of the metric Commitment Rate.
Forecast
This aggregates the values of the metric Delivery Forecast via Burn-up.
Info |
---|
Calculation notes
|
Velocity trend
Velocity trend shows a percentage of changing average velocity within last 4 weeks in comparing to the average velocity in the last 13 weeks (rolling average).
Counting method if unit start date was more than 4 weeks but less than 13 weeks ago:
Code Block | ||
---|---|---|
| ||
Average Velocity Trend = (Average Velocity for the last 4 weeks * 100%)/Average velocity for the all completed weeks from the unit start date |
Counting method if unit start date was more than 13 weeks ago:
Code Block | ||
---|---|---|
| ||
Average Velocity Trend = (Average Velocity for the last 4 weeks *100%)/Average velocity for the last 13 weeks |
Info |
---|
Calculation notes
|
Closed vs Open Defects
Closed vs Open defects shows a difference of Fixed and Opened defects (over last 4 calendar weeks) as a percentage to a number of all open defects in the backlog as of 4 calendar weeks back.
Counting method if backlog has defects:
Code Block | ||
---|---|---|
| ||
Closed vs Open Defects = (sum(Closed Defects for the last 4 weeks) - sum (Open defects for the last 4 weeks)) / Number of Defects in the backlog on the start of the last 4 weeks *100% |
Counting method if backlog has no any defects:
Code Block | ||
---|---|---|
| ||
Closed vs Open Defects (zero backlog) = (sum(Closed Defects for the last 4 weeks) - sum (Open defects for the last 4 weeks)) / 1 *100% |
Info |
---|
Calculation notes
|
Insert excerpt | ||||||||
---|---|---|---|---|---|---|---|---|
|