Scrum Cycle Time shows how much time, on average, an issue of a specific type spends in a delivery pipeline. Measured in days as a duration of appropriate sprints. Main purpose: knowing how big this timing is, it gives a chance to continuously monitor it towards improvement (acceleration).

How metric helps

Scrum Cycle Time helps understand how fast a business need is transformed to a value delivered to a client. It can be, to some extent, an idea of the "Time to Market" measure. Knowing such thing, one has more flexibility in estimations and planning. Usually, the shorter this measure, the faster things go to market (i.e. to production).

...

TOP-5 problems metric identifies 

...

  1. Unexpected blockers or Poor dependencies during Sprint execution

  2. Not ready for development backlog is taken into work

  3. Low productivity due to reduced agility

  4. Uncontrolled scope volatility

  5. Too many dependent teams

...

  1. Uncommitted Tasks sneaking into Scope during execution

Expand
titleOther

...

Schematically, here is the idea how this metric is calculated:

...

SCTsprint =∑SCTsprint_i /N,

...

Info

Example

Sprint 1 dates: Jan 2 - Jan 15

Sprint 2 dates: Jan 16 - Jan 30

Sprint 3 dates: Jan 31 - Feb 13

Sprint 4 dates: Feb 14 - Feb 28

Sprint 5 dates: Mar 1 - Mar 15

Story1 was created on Jan,1 and planned for Sprint1. The team started working on it on Jan, 5 and then on Jan, 10 it was decided to suspend development and remove it from the scope. Then on Feb,3 it was decided to work on in in Sprint4. It was started in Sprint 4 and finished on Feb, 20.

Story2 and Story3 were created on Feb,13, taken into Sprint4 iteration . Story 2 completed on Feb,25. Story 3 was completed on March,2.

Cycle Time for Story1 is Feb,28 - Jan,2 = 58 days, as Sprint4End - Sprint1Start

Cycle Time for Story2 is Feb,28 - Feb,14= 14 days as Sprint4End - Sprint4Start

Cycle Time for Story3 is Mar,15 - Feb,14 = 29 days as Sprint5End - Sprint4Start

Cycle Time for Sprint 4 = (58+14)/2 = 36 days

Cycle Time for Sprint 5 = 29/1=29 days

Unusual cases:

1 Issue completion date is earlier than a sprint start it is assigned to: issue SCTsprint is calculated by a sprint lifetime issue completion date is covered by.

2 Issue completion date is later than a sprint finish it is assigned to: issue SCTsprint is calculated by a sprint lifetime issue completion date is covered by.

3 Project has 2 active sprints in the same time and one of the sprints is started later and finished early then other. Issue is assigned to this short sprint and completion date in frame of it: issue SCTsprint is calculated by a sprint with later end date. Assigned sprint is not affected

Data Source

Data for the metric can be collected from a task tracking system (Jira, TFS, Rally etc.).

...