This section describes how to link a target with other targets to see the entire process of achieving the planned goals.
You can link targets in two Planner entities:
...
Target's sidebar
Gantt chart
1. Link in the sidebar
The information sidebar of any target contains three tables intended for linking the target with other targets.
...
Type of link
...
How to
...
Includes
...
Create a new target
...
Contributes To
...
Open the sidebar of a new or existing target.
In the Contributes To table, click Add Item, or Add Objective.
In the Title field, start typing the name of a required target, and then select the name from the system prompt.
...
Dependencies
...
Open the sidebar of a new or existing target.
In the Contributes To table, click Add Item, or Add Dependency.
In the Title field, start typing the name of a required target, and then select the name from the system prompt.
Create/Full View (Target’s sidebar)
1. Link via Gantt Chart
This section describes how to link targets in the via Gantt chart by means of dragging a connector between targets.
To link a target:
...
Hover a target. The system displays points on both ends of the target.
Click the point and drag the connector to a required target to link.
Drop the connector on the required target. The Add Connection sidebar opens.
Specify the type of link: Hard link or Soft link.
If you selected Hard link, specify the type of dependency, as one of the following:
Finish to start
Start to finish
Finish to finish
Start to start
Click Save.
...
2. Link via Create or Full View
The information sidebar of any target contains two tables intended for linking the target with other targets.
Link Type | How to link a target |
---|---|
Includes |
|
Dependencies |
|