Specifies the name of the status dimension which the risk affects.
The table lists available status dimensions in alphabetical order.

...

Status dimension

...

Alignment with client

...

GDPR_________________

...

Quality

...

Team Retention

...

Team Performance

...

Schedule

...

Scope

...

WFH Impact

Correlates with the list of Status Dimensions in the Health Status Dimensions.

2. Probability

Probability

1 - Low

2 - Medium

3 - High

3. Impact

Impact

Impact Effect

1 - Low

We could handle this without extra money/resources

2 - Medium

It will cost us money/resources to remedy

3 - High

We might lose the customer/project over this

4. Treatment Strategy

Strategy

Description

Avoidance

Risk avoidance is elimination (removal) of the risk in such a way that it is no longer applicable
to the project. It is the first choice of any risk strategy and can be done by:

  • Removing any lack of knowledge, or uncertainty that caused the risk.

  • Choosing an approach whereby the risk is no longer applicable.

Mitigation

Risk mitigating or reducing the risk by reducing the impact, or loss it can cause.
The idea is that risks are to be mitigated till the risk exposure is within “acceptable limits”.

Transfer

Risk transfer transfers the liability of the risk to a third party through contractual agreements, insurance, indemnity, warranty, and so on.
In such a way, you change ownership of the risk. There must be a proper communication and evidence of Risk Transfer.

Acceptance

Risk acceptance is accepting, or retention of the risk and is typically the response after avoidance, transfer and mitigation were considered or tried.
It is typical for minor risks, and it indicates cases where the cost of any other strategy exceeds the risk itself.
There must be a proper communication and approval of Risk Acceptance from the Management (Delivery Supervisor or Account Manager).

5. Treatment Strategy and Damage Control Plan

...

  • To learn how to use Action Items in Health, see Action Items.

6. State

State

Description

Identified

Risks that have just been identified.

In Analysis 

Risks that have been identified and for which analysis has begun.

Treatment in Progress

Risk is currently being treated.

Occurred (Issue)

Risk occurred and became an Issue. 

Resolved 

Work with risk completed.

Archived 

Risk is no longer actual. When you select the status, the risk will be hidden from the general risk table. To display risks in the Archived status, select the Archived value in the filters in the State section.

7. Checkpoint Date

Using this field it , you can set checkpoint date to manage work on risks. 
After the checkpoint date has expired, Checkpoint Past Due notification will appear in the risk signals.

...