Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Next »

This section describes how to link a target with other targets to see the entire process of achieving the planned goals.
You can link targets in two Planner entities:

  • Target's dialog box

  • Gantt chart

1. Link in the Dialog Box 

The information dialog box of any target contains three tables intended for linking the target with other targets.  

Type of link

How to

Includes 

  1. Create a new target

Contributes To 

  1. Open dialog box of a new or existing target.

  2. In the Contributes To table, click Add Item, or Add Objective.

  3. In the Title field, start typing name of a required target, and then select the name from the system prompt.

Dependencies

  1. Open dialog box of a new or existing target.

  2. In the Contributes To table, click Add Item, or Add Dependency.

  3. In the Title field, start typing name of a required target, and then select the name from the system prompt.

2. Link in the Gantt Chart

This section describes how to link targets in the Gantt chart by means of dragging a connector between targets.

To link a target:

  1. Pause on a target. The system displays points on both ends of the target.

  2. Click the point and drag the connector to a required target to link.

  3. Drop the connector on the required target. The Add Connection dialog box opens.

  4. Specify type of link: Hard link or Soft link.

  5. If you selected Hard link, specify type of dependency, as one of the following:

    • Finish to start

    • Start to finish

    • Finish to finish

    • Start to start

  6. Click Save.

  • No labels