1. Types of Targets
There are four types of targets in the Planner application: OKR, Key Result, Initiative, and Milestone.
Type of target | Description | Example |
---|---|---|
OKR | An Objective according to the OKR methodology, this is a big and ambitious goal. An OKR is to be formulated as a short sentence, understandable for the entire team. The grade of achieving this goal is measured by Key Results. | Increase system performance. |
Key Result | A desired result after performing a series of actions. Reaching the result, you can understand how much the OKR is accomplished. Key result can be measured by percent or quantity of something. | Increase the ability for users to work simultaneously by 15%.
|
Initiative | A small goal or a specific action you need to do for achieving a small goal (other Initiative), Key Result or bigger goal (OKR). | Perform regression testing to identify critical errors. |
Milestone | A scheduled end date when the planned goals and results are to be achieved. | Planned release 29.03.2022. |
2. Types of Relationships
In the Planner application there are two types of links.
Type of Link | Description | Type of Relationship |
---|---|---|
Hard link |
|
|
Soft link |
This type shows that the work for achieving common results is performed at the same area. |
|
2.1 Hard Link
This section describes types of relationship for a hard link in more details.
2.1.1 Parent-Child Relationship
This type of relationship is available for OKR → Key Result, Initiative → Initiative, Milestone → Initiative, and Initiative → Milestone.
The parent-child relationship can be applied to the targets that belong to the same unit.
Constraints of parent-child relationship
An OKR target cannot have a parent target.
A Key Result target cannot have child targets.
Initiatives and Milestones can have as many nested levels of targets as you need.
Each parent target inherits the progress of child targets.
2.1.2 Dependencies (Time Dependencies)
This type of relationships is available only for Initiatives and Milestones, which can belong to different units.
There are four time dependencies:
Dependency | Description |
---|---|
Finish to start | The linked target must be started in the same day when the main target is finished |
Start to finish | The linked target must be finished in the same day when the main target is started |
Finish to finish | Both linked targets must be finished in the same day |
Start to start | Both linked targets must be started in the same day |
When you move a target that have any time dependencies, the system moves linked targets in order to save correct time dependency.
2.2 Soft Link
This section describes types of relationship for a soft link in more details.
Both the Contribute To and Contribute By types of relationship are available for targets in different units.
2.2.1 Contributes To Relationship
The Contributes To type of relationship is available for such types of targets as:
OKR → OKR;
Initiative or Milestone → OKR, Key Result, Initiative, Milestone.
This type of relationship shows, that the target you try to link with others, contributes to the achieving results that planned in the linked targets.
Example: You have the target "To set advertising campaign to attract a new audience" and it contributes to the target "To increase the number of active users by 30%".
2.2.2 Contributes By Relationship
The Contributes By type of relationship is available for such types of targets as:
OKR ← OKR, Initiative;
Key Result ← Initiative or Milestone;
Initiative or Milestone ← Initiative or Milestone.
This type of relationship shows, that the target you try to link with others, gets contribution in its results from the linked targets.
The Contributes By type of relationship is opposite to the Contributes To type.
3. Color Indication of Gantt Chart
The Planner Gantt chart uses four colors to display status and progress of the workflow targets.
Status Name and Color | Description |
---|---|
GRAY
| NOT STARTED The target doesn't have a progress and and its start date is in the future |
GREEN
| ON TRACK The target has a progress and it goes according to the plan OR COMPLETE The target is accomplished and the progress is 100% |
ORANGE
| AT RISK Displays an incomplete target (it may have progress or not) but it goes slightly not according to plan |
RED
| OFF TRACK The target is incomplete and in a dangerous state |