This section describes how to link a target with other targets to see the entire process of achieving the planned goals.
You can link targets in two Planner entities:
Create View
Full View (Target’s sidebar)
Gantt chart
1. Link via Create or Full View
The information sidebar of any target contains two tables intended for linking the target with other targets.
Type of link | How to |
---|---|
Includes |
|
Dependencies |
|
2. Link via Gantt Chart
This section describes how to link targets in the Gantt chart by means of dragging a connector between targets.
To link a target:
Pause on a target. The system displays points on both ends of the target.
Click the point and drag the connector to a required target to link.
Drop the connector on the required target. The Add Connection sidebar opens.
Specify the type of link: Hard link or Soft link.
If you selected Hard link, specify the type of dependency, as one of the following:
Finish to start
Start to finish
Finish to finish
Start to start
Click Save.