Snapshots

Snapshots

This chapter describes how to handle snapshots in the Planner application.

Snapshot provides a visual comparison between an initial state of the timeline (baseline) and a modified state.
When applied, the baseline looks like dark grey lines below the targets of the modified timeline.

1. Create a Snapshot

To create a new snapshot:

  1. On the Planner Action Bar, click image-20241010-181331.pngTake a Snapshot” button “Create New Snapshot” →
    The Snapshot Name dialogue box opens.

  2. Enter the snapshot name, and then click Add. The system creates a snapshot of the current state of the timeline.

2. Apply a Snapshot

To apply a snapshot:

  1. On the Planner Action Bar, click image-20241010-181331.pngTake a Snapshot” button → the dialogue box opens.

  2. In the dialogue box, select the check box of the snapshot you want to apply → The system applies the selected snapshot. See Fig. 1.

 

image-20241010-181748.png
Fig. 1. Apply a snapshot

 

3. Delete a Snapshot

To delete a snapshot:

  1. On the Planner Action Bar, click  image-20241010-181331.pngTake a Snapshot” button → The dialogue box opens.

  2. Click image-20241010-181945.png Delete button (“backet”) → The confirmation dialogue opens.

  3. Click Delete button to confirm, that you want to delete the snapshot → The system deletes the selected snapshot.

4. Share a Snapshot

To copy a link to a snapshot:

  1. On the Planner Action Bar, click image-20241010-181331.pngTake a Snapshot” button → The dialogue box opens.

  2. Click image-20241010-182124.png Share Link button → The system saves the snapshot link to the clipboard.

 

Related content

Getting Started
Getting Started
More like this
Planner Application User Guide
Planner Application User Guide
More like this
Create Target
More like this
Filter, Sort Targets
Filter, Sort Targets
More like this
Link Target
More like this
Show / Hide Elements in Timeline and List
Show / Hide Elements in Timeline and List
More like this