Effort Logged on Completion
Purpose
Effort Logged on Completion shows a percentage of completed items closed within last 90 days and have any effort logged in a task tracking system.
How metric helps
Effort Logged on Completion helps to identify items without a logged effort.
How metric works
Chart overview
Chart shows a percentage of items with a logged time before its completion.
By click on a column a pop up appears with the following information:
Issue ID
Type
Priority
Summary
Calculation
Effort Logged on Completion is (a number of items in a "Done" status with a logged time divided by a number of all "Done" items) * 100 %.
RAG thresholds: Red - metric value < 95 %; Green - metric value >=95 %.
Assumptions
1 Calculation considers completed items within the last 90 days.
2 "Done" status is a status from "Done" bucket in Project Settings>Data Sources>Task Tracking System>Workflow.
Data Source
Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).