1. Types of Targets

There are several types of targets in the Planner application, according to the table below

Type of target

Description

Example

Objective

Objective according to the OKR methodology, this is a big and ambitious goal. An Objective is to be formulated as a short sentence, understandable for the entire team. The grade for achieving this goal is measured by Key Results.

Increase system performance.

Key Result

The desired result after performing a series of actions. Reaching the result, you can understand how much the Objective is accomplished. The key result can be measured by the per cent or quantity of something.

Progress of a Key Result directly affects progress
of a parent Objective

Increase the ability for users to work simultaneously by 15%.

 

Initiative

A small goal or a specific action you need to do to achieve a small goal (other Initiative), Key Result or bigger goal (Objective).

Please, pay attention, that at the moment
progress of an Initiative doesn’t affect progress
of a Key Result/Objective

Perform regression testing to identify critical errors.

Milestone

A scheduled end date is when the planned goals and results are to be achieved.

Please, pay attention, that at the moment
progress of a Milestone doesn’t affect progress
of a Key Result/Objective

Planned release 29.03.2022.

2. Types of Relationships

In the Planner application, there are three types of links:

Type of Link

Description

Parent-Child

  • Targets become dependent on each other, and a period of a parent target includes periods of all child targets.

  • The change of a child target's period leads to a change in a parent target's period

Dependencies (Start/Finish) 

  • Targets are dependent in start/finish. See 2.1.1 Dependencies (Start/Finish)

Contribution

  • Targets are independent.

  • A change in one target doesn't lead to a change in the other connected targets.

This type shows that the work for achieving common results is performed in the same area

2.1 Parent-Child

image-20240206-162837.png

Constraints of the parent-child relationship:

  • An Objective target cannot have a parent target. Only Key Results can be children to an Objective.

  • A Key Result target cannot have child targets.

  • Initiatives can have as many nested levels of targets as you need.

  • Each parent target inherits the progress of child targets.

The parent-child relationship can be applied to the targets that belong to the same unit.

2.1.1 Dependencies (Start/Finish)

Time dependencies are available only for Initiatives and Milestones, which can belong to different units.

There are four-time dependencies:

Dependency

Description

Finish to start

The linked target must be started on the same day when the main target is finished

Start to finish

The linked target must be finished on the same day when the main target is started

Finish to finish 

Both linked targets must be finished on the same day

Start to start 

Both linked targets must be started on the same day

When you move a target that has any time dependencies, the system moves linked targets to save the correct time dependency.

2.2 Contribution

2.2.1 Contributes To

The Contributes To the type of relationship is available for such types of targets as:

  • Objective Objective;

  • Initiative or Milestone Objective, Key Result, Initiative, Milestone.

This type of relationship shows that the target you try to link with others, contributes to the achieving results that are planned in the linked targets.

Example: You have the target "To set advertising campaign to attract a new audience" and it contributes to the target "To increase the number of active users by 30%".

3. Color Indication of Gantt Chart

The Planner Gantt chart uses four colors to display the status and progress of the workflow targets.

Status Name and Color

Description

GRAY

 

NOT STARTED

The target doesn't have progress and its start date is in the future

GREEN

 

 

ON TRACK

The target has progressed and it goes according to the plan

OR

COMPLETE

The target is accomplished and the progress is 100%

ORANGE (AMBER)

 

 

AT RISK 

Displays an incomplete target (it may have progressed or not),
but it goes slightly not according to plan (if there is any difference between expected completion and actual completion and the difference is less than 25 percent)

RED

 

OFF TRACK

The target is incomplete and in a dangerous state (if actual completion doesn't meet expected completion in more than 25 percent)