This section describes how to update target progress through check-in. You can check in a target from the following Planner entities:
Planner List view
Target information sidebar
Planner Timeline view
1. List View Check In
.To check in a target in the List view:
In the right or the required target row, click ⋮ (ellipsis), and then click Check in. The Check-In sidebar opens.
In the Current Progress specify the target progress in %.
Click Check-In.
You cannot directly update the progress of a parent target having child targets. To do that you need to update the progress of the child targets.
2. Target sidebar Check In
To check in a target in the List view:
Open the sidebar of the required target.
In the upper left, click Check in. The Check-In opens.
In the Current Progress specify the target progress in %. See Fig. 2.
Click Check-In.
You cannot directly update the progress of a parent target having child targets. To do that you need to update the progress of the child targets.
3. Planner Timeline view
To change the progress of a target:
Pause on a target. The system displays the progress grip ꕔ (triangle) on the target line.
Drag the progress grip.