Tasks Not Estimated But Effort Logged is a number of items, where an item satisfies the criteria: estimate filed (in SP/Hours) of an item is empty or "0", but effort is logged.


RAG thresholds:  Red - metric value > 0; Green - metric value = 0. 

Info
titleAssumptions

1 Estimate field for an item to track an estimate absence is taken from Project Settings>Data Sources>Task Tracking System>Scope Management>Issue types to be estimated in Story Points/Man hours. 

2 If an issue/work item type is selected in Issue types to be estimated in Story Points, "0" value in

...

Story Points field is to be considered. 

...

3 Field for estimates to be checked is set in Project Settings>Data Sources>Task Tracking System>Fields mapping.

Data Source

Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).

...