Purpose
Items in Progress with no Changes During Last 2 Weeks shows a number of items that are taken into work but without changes during last 2 weeks (comments, status change, work logs ,etc.).
How metric helps
Items in Progress with no Changes During Last 2 Weeks helps to prevent to prevent difficulties related to tasks without changes and take actions to complete work in time.
How metric works
Chart overview
Chart shows a number of items that are taken into work but without changes for the last 2 weeks - number in center. Target Target value is above the chart.
By click on a chart a pop up appears with the following information got from the task tracking system:
- Issue ID
- Type
- Priority
- Summary
Calculation
Items in Progress with no Changes During Last 2 Weeks is a number of items in a "In Progress" status without changes. me me logs added, comments added, details changed
RAG thresholds: Red - metric value > 0; Green - metric value = 0.
Info | ||
---|---|---|
| ||
1 Calculation considers items being in progress for the last 2 weeks. 2 Change in the work logs, description, comments are considered. 2 "Include sub items into metrics calculation" setting affects this metric.3 "In Progress" status is a status from "In Progress" bucket in Project Settings>Data Sources>Task Tracking System>Workflows. |
Data Source
Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).