Number of Issues in Backlog (out of Sprints) but Already Completed shows the amount of issues items at the moment which are already completed in the backlog but not assigned to any a sprint.
How metric helps
Number of Issues in Backlog (out of Sprints) but Already Completed helps to point out loss in a contribution lost from sprint velocity. It is expected that on the project this health indicator value is equal to zero.
Only valid items are counted here i.e. such ones like "Duplicate", "Rejected", "Cannot reproduce" or similar are not taken into consideration. The expected metric value is 0.
How metric works
Chart overview
Chart shows Number of Issues in Backlog (out of Sprints) but Already Completed in amount of shows a number of completed items without an assignment to a sprint - number in the center. Target value is above the chart.
...
By click on a chart a pop up appears with the following information got from the task tracking system:
Issue ID
Type
Priority
Summary
Calculation
Number of Issues in Backlog (out of Sprints) but Already Completed is measured as a number of items in a "ClosedDone" status which haven't sprint (sprint where a sprint field value is empty ) and exclude invalid items (resolution not in "Won't Fix", "Duplicate", "Cannot Reproduce", "Rejected", "Abandoned - No Consensus", "Obsolete", "Expired", "Won't Do", "Project Closed", "Out of scope", "Canceled")excluding invalid defects.
RAG thresholds: Red - metric value > 0; Green - metric value = 0.
Info |
---|
Assumptions1 Calculation considers all completed items got from the task tracking system. 2 "Done" status is a status from "Done" bucket in Project Settings>Data Sources>Task Tracking System>Workflow. 3 Invalid defect is a defect with a resolution selected in Project Settings>Data Sources>Task Tracking System>Quality Management>Criteria for invalid defects. |
Data Source
Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).
Insert excerpt | ||||||||
---|---|---|---|---|---|---|---|---|
|