Chart shows a number of days it usually takes for a defect to be fixed - number in the center. Target value is above the chart.
...
By click on a chart a pop up appears with the following information got from the task tracking system:
Issue ID
Type
Priority
Summary
Calculation
Defects Average Lifetime (all priorities) = (number of days defects were in not "Done" status/ number of all defects).
RAG thresholds: Red - metric value > 30; Green - metric value = < 30.
Info | |
---|---|
title | Assumptions1 Calculation considers closed items within the last 90 days. 2 Defect is an item of a type set in Project Configuration > Data Sources > Task Tracking System> Quality Scope Management > Issue/Work Item type used for defects tracking.Definition of Work Buckets > Defects 3 "Done" status is a status from "Done" bucket in Project Settings>Data Sources>Task Tracking System>Workflows. 4 Invalid defects are excluded from the calculation. Invalid defect is that conforms to Project Settings ->Data Sources ->Task Tracking System ->Quality Management ->Criteria for invalid defects. |
Data Source
Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).