Purpose

Number of Issues in Backlog (out of Sprints) but Already Completed shows the amount of items at the moment which are completed but not assigned to a sprint.

How metric helps

Number of Issues in Backlog (out of Sprints) but Already Completed helps to point out loss in a sprint velocity. The expected metric value is 0.

How metric works

Chart overview 

Chart shows a number of completed items without an assignment to a sprint - number in the center. Target value is above the chart.  


By click on a chart a pop up appears with the following information got from the task tracking system: 

  • Issue ID
  • Type
  • Priority
  • Summary

Calculation

Number of Issues in Backlog (out of Sprints) but Already Completed is a number of items in a "Done" status where a sprint field value is empty and excluding invalid defects.

RAG thresholds:  Red - metric value > 0; Green - metric value = 0. 

Assumptions

1 Calculation considers all completed items got from the task tracking system.

2 "Done" status is a status from "Done" bucket in Project Settings>Data Sources>Task Tracking System>Workflow.

3 Invalid defect is a defect with a resolution selected in Project Settings>Data Sources>Task Tracking System>Quality Management>Criteria for invalid defects

Data Source

Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).