Purpose
Stories Which Are Open/Ready State But With All Sub-tasks Already Closed shows the amount of stories (and other issues) which are still in Open/Ready/In Progress status but with all their sub-tasks closed. Calculation is based on issues created within last 90 days.
How metric helps
Stories Which Are Open/Ready State But With All Sub-tasks Already Closed helps to highlight an issue with wrong stories' statuses.
It is expected that on the project this health indicator value is equal to zero.
How metric works
Chart overview
Chart shows Stories Which Are Open/Ready State But With All Sub-tasks Already Closed in amount of active stories (and other issues) but with already closed sub-tasks.
By click on a chart a pop up appears with the following information got from the task tracking system:
- Issue ID
- Type
- Priority
- Summary
Calculation
Stories Which Are Open/Ready State But With All Sub-tasks Already Closed calculates a number of issues like Story, Task, Improvement etc (issues that have sub-tasks). that are in not completed status, but with completed sub-tasks.
Calculation is based on issues created within last 90 days.
RAG thresholds: Red - metric value > 0; Green - metric value = 0.
Data Source
Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).