Purpose

Unresolved Bugs Older Than a Month (top priorities) shows a number of open defects of a top priority for today with a lifetime more than a month.

How metric helps

Unresolved Bugs Older Than a Month (top priorities) reveals a number of open top priority defects living more than a month so that they have to be take into work immediately. The expected value is equal to zero.

How metric works

Chart overview

Chart shows a number a number of open defects of a top priority with a lifetime more than a month - number in the center. Target value is above the chart.  

By click on a chart a pop up appears with the following information got from the task tracking system: 

  • Issue ID
  • Type
  • Priority
  • Summary

Calculation

Unresolved Bugs Older Than a Month (top priorities) is a number of defects of a top priority being in not "Done" status for the last 30 days.

RAG thresholds:  Red - metric value > 0; Green - metric value = 0. 

Assumptions

Calculation considers created items within the last 90 days.

2 Defect is an item of a type set in Project Configuration > Data Sources > Task Tracking System> Quality Management > Issue/Work Item type used for defects tracking.

3 Top priority defect is a defect of a priority defined in Project Settings > Data Sources > Task Tracking System > Quality management.

4 "Include sub items into metrics calculation" setting affects this metric. 

5 "Done" status is a status from "Done" bucket in Project Settings>Data Sources>Task Tracking System>Workflows.

Data Source

Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).

See also