Effort Logged on Completion

Purpose

Effort Logged on Completion shows a percentage of completed items closed within last 90 days and have any effort logged in a task tracking system.

How metric helps 

Effort Logged on Completion helps to identify items without a logged effort.

How metric works 

Chart overview

Chart shows a percentage of items with a logged time before its completion.

By click on a column a pop up appears with the following information:

  • Issue ID

  • Type

  • Priority

  • Summary

Calculation

Effort Logged on Completion is (a number of items in a "Done" status with a logged time divided by a number of all "Done" items) * 100 %.

RAG thresholds: Red - metric value < 95 %; Green - metric value >=95 %. 

Assumptions

1 Calculation considers completed items within the last 90 days.

2 "Done" status is a status from "Done" bucket in Project Settings>Data Sources>Task Tracking System>Workflow.

Data Source

Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).