Purpose
Stories Which Are Closed But With Any Sub-tasks Still Incomplete shows a number of completed items with incomplete sub items.
How metric helps
Stories Which Are Closed But With Any Sub-tasks Still Incomplete helps to highlight an issue with wrong items statuses. Wrong status of an item may affect the progress metrics like Velocity, Burn up. The expected metric value is 0.
How metric works
Chart overview
Chart shows a number of completed items with incomplete sub items - number in the center. Target value is above the chart.
By click on a chart a pop up appears with the following information got from the task tracking system:
- Issue ID
- Type
- Priority
- Summary
Calculation
Stories Which Are Closed But With Any Sub-tasks Still Incomplete is a number of parent items with sub items in not "Done" status.
RAG thresholds: Red - metric value > 0; Green - metric value = 0.
Assumptions
1 Metric shows values for the items created within the last 90 days.
2 "Include sub items into metrics calculation" setting affects this metric. If it's not applied, metric will show 0.
3 "Done" status is a status from "Done" bucket in Project Settings>Data Sources>Task Tracking System>Workflows.
Data Source
Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).