Chart shows a percentage of time spent on fixing defects - number in the center. Target value is is above the chart.
...
By click on a chart a pop up appears with the following information got from the task tracking system:
Issue ID
Type
Priority
Summary
Calculation
Time Spent On Bug Fixing = (time logged for defects / all logged time) *100.
RAG thresholds: Red - metric value > 20; Green - metric value = < 20.
Info | |
---|---|
title | Assumptions1 Calculation considers created items within the last 90 days. 2 Defect is an item of a type set in Project Configuration > Data Sources > Task Tracking System> Quality Management > Issue/Work Item type used for defects tracking. |
Data Source
Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).
See also
Insert excerpt | ||||||||
---|---|---|---|---|---|---|---|---|
|