Purpose

Backlog Health shows the amount of a ready scope (i.e. scope in the "Ready for Development" state) at the start of each sprint. The scope may be measured in originally estimated hours or story points.

How metric helps

Backlog Health:

  • shows how many sprints of "ready for development" work a team possesses

  • helps to evaluate scope gathering and requirements management process

  • helps to understand whether the client/customer is able to provide enough details to form a backlog

  • shows how reachable Definition of Ready is, i.e. no issues in the estimation process, designs and specification are provided, INVEST principles easily followed

  • whether PO is engaged / available enough to manage backlog including priorities

  • shows whether the team is able to identify and define technical requirements to get tech tasks to a status of "ready for development"

  • shows whether there is an actual roadmap preserved and a clear product goal set to have backlog items in order

  • shows whether there is any risk that refined requirements can be subject to change and revisited moving forward

  • shows how effective feature refinement and estimation process is

Benefits:

  • make sure the business team provides enough requirements to backlog about feature development

  • make sure the engineering team conducts timely refinement and estimation of requirements

How metric works

Chart overview

The chart shows Backlog Health in a number of sprints scope is ready ahead - Axis Y by sprints in time - Axis X.

On hover over a column a hint appears with the following info: 

  • Sum of story points/original hours for the items in a ready status;

  • Number of items by type;

  • Average team velocity;

  • Metric value.

Chart legend shows the latest metric value and the difference between this value and the previous one.

By click on a column a pop up appears with the following information got from the task tracking system: 

  • Issue ID

  • Type

  • Priority

  • Summary.

Sprints on the widget are sorted by the sprint start date, as the metric is calculated at a sprint start.

Not estimated and issues with 0 estimate are not displayed in the pop up and not included in the calculation.

What metric means

  1. [Below ideal, <5] Absence of roadmap, no vision

  2. [Below ideal, <5] Poor requirements provisioning process

  3. [Below ideal, <5] Too many dependent teams

  4. [Below ideal, <5] Scope cannot be properly estimated

  5. [Below ideal, <5] PO is not involved enough into Sprint execution

 Other
  • [Below ideal, <5] Features cannot be broken down to follow INVEST principles

  • [Below ideal, <5] Weak demand intake flow, the process when an idea gets into product backlog is not properly defined 

  • [Below ideal, <5] Multiple stakeholders influence priorities, leading the backlog mess

  • [Below ideal, <5] Rapid priority / roadmap changes 

  • [Below ideal, <5] There are mixed roles between SM, PO, BA in backlog management, so no unique approach in preparing and moving story to the definition of ready

  • [Below ideal, <5] Team does not possess enough technical background to specify technical requirements 

  • [Below ideal, <5] Team setup / composition misbalance (skills ratio)

  • [Above ideal, >5] Low velocity of the team, so the backlog is being burnt out slowly 

  • [Above ideal, >5] There are too many requests and ideas brainstormed in advance, and being provided as requirements, groomed, and estimated as user stories, however not planned far away

  • [Above ideal, >5] There are several streams/teams using the same backlog

Calculation

Backlog Health =∑Eready/Vavg,

where

∑Eready - estimates sum for N ready for development tasks at a sprint start. Ready state is according to criteria in Project settings>Scope management>Definition of Ready.

Vavg - average velocity for the last N periods; N periods  - taken from Project settings>Scope management> Calculation depth for average team velocity estimation.

RAG thresholds: Red - metric value <=1; Amber - 1 < metric value<=2; Green - 2 < metric value <=5; Amber - metric value >5.

Calculation notes

1. Issues that got a ready state before a considered sprint start timestamp are included into the calculation regardless of their assignment to another sprint.

2. Average velocity assumptions:

  • Incomplete (current) sprint is not taken into account;

  • Estimate is taken at an issue completion;

  • Not estimated and null estimates are not included in the calculation;

  • Sub-items are not included in the calculation.

3. Trend line (blue dotted line) calculation (its inclination to axis x) ignores an incomplete iteration in the chart to reveal an accurate tendency.

4. If there are several active sprints are running simultaneously in one project, the Backlog health value is calculated only for the first one.

Example

There are 2 sprints:

  • Current sprint S1: start on Dec 1.

  • Next sprint S2 : start on Dec 14.

There is an issue A that has got a ready state on Nov 30 but assigned to S2.

Issue A will be included in the calculation of Backlog Health for S1 and can be viewed in the drill-down for this sprint.

Data source 

Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).

See also 

Copyright © 2024 EPAM Systems, Inc.

All Rights Reserved. All information contained herein is, and remains the property of EPAM Systems, Inc. and/or its suppliers and is protected by international intellectual property law. Dissemination of this information or reproduction of this material is strictly forbidden, unless prior written permission is obtained from EPAM Systems, Inc.