Risk Parameters
Set Parameters of New Risk
This section belongs to Risk Management in Health. It describes how to select values of new risk parameters according to risk management approach.
1. Status Dimension
Specifies the name of the status dimension which the risk affects. Correlates with the list of Status Dimensions in the Health Status Dimensions.
2. Probability
Probability |
---|
1 - Low |
2 - Medium |
3 - High |
3. Impact
Impact | Impact Effect |
---|---|
1 - Low | We could handle this without extra money/resources |
2 - Medium | It will cost us money/resources to remedy |
3 - High | We might lose the customer/project over this |
4. Treatment Strategy
Strategy | Description |
---|---|
Avoidance | Risk avoidance is elimination (removal) of the risk in such a way that it is no longer applicable
|
Mitigation | Risk mitigating or reducing the risk by reducing the impact, or loss it can cause. |
Transfer | Risk transfer transfers the liability of the risk to a third party through contractual agreements, insurance, indemnity, warranty, and so on. |
Acceptance | Risk acceptance is accepting, or retention of the risk and is typically the response after avoidance, transfer and mitigation were considered or tried. |
5. Treatment Strategy and Damage Control Plan
Using the in-built rich text editor, type in the following textual information:
Relevant details of the chosen risk treatment strategy.
Action items to support the chosen strategy.
Damage Control Plan
To select any action item of risk treatment strategy as Done, you need to open the Edit Risk Details dialog box.
See also:
To learn how to use Action Items in Health, see Action Items.
6. State
State | Description |
---|---|
Identified | Risks that have just been identified. |
In Analysis | Risks that have been identified and for which analysis has begun. |
Treatment in Progress | Risk is currently being treated. |
Occurred (Issue) | Risk occurred and became an Issue. |
Resolved | Work with risk completed. |
Archived | Risk is no longer actual. When you select the status, the risk will be hidden from the general risk table. To display risks in the Archived status, select the Archived value in the filters in the State section. |
7. Checkpoint Date
Using this field, you can set checkpoint date to manage work on risks.
After the checkpoint date has expired, Checkpoint Past Due notification will appear in the risk signals.
Checkpoint date is an optional field. By default, the system sets the date according to the formula: Current date + 2 weeks.