Estimated Items in Story Points at Sprint Start

Purpose

Estimated Items in Story Points at Sprint Start shows the percentage of estimated items (in Story Points) at a sprint start date and time.

How metric helps 

Estimated Items in Story Points at Sprint Start helps to identify that all items in for an active sprint are estimated.

How metric works

Chart overview 

Chart shows a percentage of estimated items in Story Points at at a sprint start date - number in the center. Target value is above the chart.  

By click on a column a pop up appears with the following information:

  • Issue ID

  • Type

  • Priority

  • Summary

Calculation

Estimated Items in Story Points at Sprint Start = (Number of estimated items in Story Points at a sprint start date and time/ Amount all items in a sprint)*100%

RAG thresholds: Green - metric value >= 95%, Red - metric value <95 %.

Assumptions

1 Calculation considers the latest active sprint. If there are several active sprints, metric sums up values for all sprints. Assignment to a sprint matters.

2 Field for estimates is set in Project Settings>Data Sources>Task Tracking System>Fields mapping.

3 Issue/work item types taken into the calculation: those selected in Project Settings>Data Sources>Task Tracking System>Scope Management>Issue types to be estimated in Story Points . 

Data Source 

Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).