Velocity difference between PERF and JIRA

Velocity difference between PERF and JIRA

Measurement of a Velocity might differ between PERF and JIRA. There are some reasons for it. One of root causes: the flexibility in tuning of a project configuration in PERF (which may directly influence how velocity is computed, as well as other metrics) is way higher than in JIRA. 

Examples of situations where a velocity of a team can be different between PERF and JIRA:



REASON

EXAMPLE

WHAT TO DO

1

Data in PERF is not up-to-date i.e. after last data load some changes were made in JIRA

JIRA: some stories were completed in a sprint during last day, but those updates are not yet propagated to PERF.

Run data load in PERF on appropriate data source.

2

Definition of Done in PERF (i.e. statuses for a "Done" bucket at the Workflows) is different from what JIRA uses by default i.e. a discrepancy in interpretation

JIRA: checks velocity by Resolved status

PERF: "Resolved" status on some projects can be a part of the "In Progress" bucket intentionally, only "Closed" status can be used for "Done" bucket - for a better accuracy of a velocity on a project (e.g. "Closed" means acceptance by a Product Owner while "Resolved" is only about development completion, but not yet tested/documented/demonstrated/etc.)

Review workflows configuration in PERF and either

a) accept it and use PERF interpretation of velocity going forward or

b) align workflows in PERF to JIRA

3

Effort estimations (e.g. in Story Points) are used at Sub-task level too, not only in master issues

JIRA: team puts story points into Stories, Tasks, Sub-tasks. But JIRA computes velocity only by master issues e.g. by Stories and Tasks in this example, i.e. excluding Sub-tasks.

PERF: velocity is calculated as cumulative value - across Stories, Tasks and Sub-tasks i.e. will be greater than velocity in JIRA

Consider one of the following:

a) stop using SP estimates for sub-tasks, use SP only on the level of master issues (as per best practices). If you need estimations for sub-tasks then use man hours.

b) create a new filter in JIRA which excludes sub-tasks to eliminate the source of discrepancy for PERF - and use that filter for a respective project (or node) in PERF

c) adjust a configuration of the project in PERF to "ignore" sub-task issue types so that their SPs to not impact an overall velocity

4

Reopened issues processing

An issue is completed in sprint A but reopened after sprint A end and then closed without an assignment to another sprint.

JIRA: issue is included into completed issues in sprint A.

PERF: issues won't appear in completed issues in sprint A.

a) assign the issue to another sprint;

b) for editing issues attributes (component, labels, etc.) do not re-open issues, it's better to contact Jira support.

5

Issues closed after a sprint end

 

 

An issue is completed in sprint A but closed after its end.

JIRA: issue is included into completed issues in sprint A.

PERF: issues won't appear in completed issues in sprint A.

a) move a sprint end date;

b) assign to the next sprint.



6

Different filter is used to query the data - in PERF jira data source vs. JIRA board 

Upon initial setup of JIRA data source in PERF, some specific JQL was put into "Advanced Filtering" section of a data source. 

Later, in JIRA, that filter for a team/board was modified (e.g. components got changed). But in PERF the old query remained. As a result, different filter queries bring different data for metrics, so metrics in Jira vs. Perf differ significantly. 

Keep a filter in PERF identical to one in JIRA. 

To reduce maintenance effort, it's recommended in PERF avoid using "by JQL" - and use "by Filter ID" instead. In this case (by Filter ID) the content of a filter remains in one place (in JIRA), so in case of any changes in it you don't need any additional actions in PERF. 

Related content

Perf Application User Guide
Perf Application User Guide
More like this
Velocity: Committed vs. Completed
Velocity: Committed vs. Completed
More like this
Obtaining Jira Filter ID for a Project / Agile Board
Obtaining Jira Filter ID for a Project / Agile Board
Read with this
Available variations of Lead Time metric
Available variations of Lead Time metric
More like this
The rules of preserving Perf data during and after Jira migration from Server to Cloud
The rules of preserving Perf data during and after Jira migration from Server to Cloud