Number of Items with Effort Logged after Items Were Closed
Purpose
Number of Items with Effort Logged after Items Were Closed shows a number of closed items with a logged effort after their closure later 00:00 next day.
How metric helps
Number of Items with Effort Logged after Items Were Closed helps to identify cases of the untimely time logging. The expected metric value is 0.
How metric works
Chart overview
Chart shows a number of closed items with late time logs - number in the center. Target value is above the chart.
By click on a chart a pop up appears with the following information got from the task tracking system:
Issue ID
Type
Priority
Summary
Calculation
Number of Items with Effort Logged after Items Were Closed is a number of issues in a "Done" status where work log time later than "Done" status time.
RAG thresholds: Red - metric value > 0; Green - metric value = 0.
Assumptions
1 Metric shows values for the items created within the last 90 days.
2 "Done" status is a status from "Done" bucket in Project Settings>Data Sources>Task Tracking System>Workflows.
Data Source
Data for the metric can be collected from a task tracking system (Jira, TFS, Rally, etc.).